1. Is everyone here
  2. Open Calendars. Any vacation time coming up?
  3. Open your todo list of things outside of JIRA, how much time will that stuff take this week?
  4. Create table of capacity for the week (everyone's total hours avail for sprint work)
  5. For each person
    1. Any tasks from last week rolled over into this week?
      1. move to this week
      2. How many points left?
    2. Pick up a story from backlog, estimate points with the whole team. Move to sprint.
    3. Is this person's sprint full? If not, repeat 2. Else next person.
  6. Examine each Epic Deadline in this sprint and Re-project expected Delivery Dates using velocity in the Epic from last week

2021-05-03